TUBIZE


TUBIZE | 1988 - 2007
Hospital
Tubize-Nivelles

Renovation-Extension |
Full mission

5880 m2

Complete restructuring of a clinical become totally obsolete and no longer fulfils any of the functional and medical compliance criteria in 1987.
To achieve the complete restructuring of the building, a complex « drawers » operation has been set up which main point was to proceed "top-down" from level 4 to level -1.

Phase 1: Level 4 (administration - lab), with "asbestos removal"
Phase 2: Level 3 (24 G beds) and 2 (30 C beds), with "asbestos removal"
Phase 3: Level 1 (30 D beds)
Phase 4: Level 0 (reception – radio op. block op)
Phase 5A: Extension (consultations + sterilization)
Phase 5B: Surroundings planning
Phase 6: Level 1 (Part 1: kitchen, pharmacy, various storages)
Phase 7: Level -1 (H.T. + Radiology)
Phase 8: Compliance of the emergency department and operating block
Phase 9: level 0 - restructuring of the medical imaging department

Subcontracting: Structure engineering (BE Legrand) | Special building techniques (M.Drayers)

PO : asbl Clinique du Parc Centre Hospitalier de Tubize-Nivelles
Contract : public-private
Phases : 9
Architectes P Debaeke - MS Hubert - D Daive